Criar uma transferência de materiais

Fundo

If you need to move materials to a new storage location, you can create a materials transfer. If the status of materials changes during the transfer, 'Quantity Available' inventory counts are updated accordingly.

Coisas a considerar

  • Permissões de usuário necessárias

  • Você pode ter vários itens de linha com locais diferentes em uma única transferência.

  • After you submit a transfer and the status is 'Final', you can only edit the following fields:

    • Attach files

    • Campos Personalizados

    • Obs.

    • Post Transfer Condition

  • 'Quantity Available' counts are updated when the transfer is submitted and the status is 'Final'.

  • Post-Transfer Item Condition

    • Quantities of 'Acceptable' materials are included in the 'Quantity Available' in your inventory.

    • Quantities of 'Damaged' and 'Unacceptable' Materials are excluded from the 'Quantity Available' in your inventory.

Pré-requisitos

Passos

  1. Navigate to the project's Materials tool.

  2. Click the Inventory tab.

  3. Mark the checkbox next to the materials you want to transfer.

  4. Click Add to New Document and select Transfer.

  5. Select Transfer.

  6. Enter the general transfer information.

    Mostrar/ocultar campos

    • Transfer Name. The name of the transfer.

    • Notes. Notes about the transfer.

    • Attachments. Upload any attachments related to the transfer.

      1. Click Attach File.

      2. Select the file and click Open to attach it.

  7. Enter the transfer for each line item.

    Mostrar/ocultar campos

    1. Select the From Location where you are transferring the materials from.

    2. Select the Pre-Transfer Condition.

      • Acceptable

      • Danificado

      • Unacceptable

    3. Enter the Quantity of items to transfer.

    4. Select the To Location where you are transferring the materials to.

    5. Select the Post-Transfer Condition.

      • Acceptable

      • Danificado

      • Unacceptable

    6. Enter any Notes.

  8. Save or submit the transfer.

    1. Click Save as Draft to save the adjustment as a draft.

    2. Click Submit to submit the adjustment as final.