Criar entradas de relatório diário de construção

Objetivo

Criar entradas do Relatório Diário de Construção na ferramenta Registro Diário do projeto.

Histórico

The Daily Construction Report section allows you to track the total number of workers and hours worked for each vendor or company and trade on a project. Additional categories for workforce labor can be configured in the Company Admin tool to use on projects. See How do I enable additional workforce labor types for the Daily Log?

Coisas a considerar

  • Permissões de usuário necessárias:
  • Informações adicionais:
    • As entradas feitas pelos colaboradores são marcadas como "pendentes" até que sejam aprovadas por um administrador.
    • É possível adicionar outras categorias de mão de obra da força de trabalho ao Relatório diário de construção no RDO: (p. ex., Mulheres, Veteranos, Minorias, Aprendiz do primeiro ano, Local (cidade) e Local (município)). Para rastrear as horas desses tipos adicionais de mão de obra da força de trabalho, primeiro é necessário configurar esses campos na seção RDO (Relatório diário de obra) da ferramenta Administrador da empresa e, em seguida, aplicados a um ou mais projetos. Consulte Como habilito tipos adicionais de mão de obra da força de trabalho para o RDO?
      Obs.: após configurada e aplicada, uma coluna "Horas de força de trabalho" ficará disponível com um link para o link "Adicionar horas" na seção Relatório diário de construção.

Passos

  1. Acesse a ferramenta RDO do projeto.
  2. Vá até a seção Relatório Diário de Construção.
  3. Preencha os seguintes campos conforme apropriado:
    Dica! Certos campos no registro do Relatório Diário de Construção podem ser configurados como obrigatórios, opcionais ou ocultos na ferramenta Admin de nível de empresa. Consulte Criar novos conjuntos de campos configuráveis.
    • #: This uneditable field counts the number of entries in a section (e.g. the first entry created will be # 1, and the second entry will be # 2).

    • Company: Select the company name from the drop-down menu. Companies must be added to the Directory tool to be selected in this drop-down menu. See Add a Company to the Project Directory.

    • Trade: Select the trade associated with the entry from the drop-down menu. You can only select from the trades already added to the project. See Add a Custom Trade.

    • Foreman: Enter the total number of foremen on-site that day followed by the total number of hours worked.

    • Journeyman: Enter the total number of journeymen on-site that day followed by the total number of hours worked.

    • Apprentice: Enter the total number of apprentices on-site that day followed by the total number of hours worked.

    • Others: Enter the number of any other workers and the total number of hours worked.

    • Comments: Enter any comments that may help clarify the entry.

    • Attachments: Attach any additional files to the entry. Click Attach File(s) and then drag-and-drop a file from your computer to the Drag and Drop your File(s) area, or click Upload Files to select a file from your computer. Once you save your item, users will be able to view the attachment in Procore's viewer or download the attachment. 

  4. Opcional: Se campos adicionais "Horas da força de trabalho" tiverem sido configurados na ferramenta Administrador de nível de empresa, você verá um link "Adicionar horas". Consulte Como habilito tipos adicionais de mão de obra de força de trabalho para o RDO?

    dl-dcr-add-hours.png
    1. Clique no link Adicionar horas .
    2. Insira as horas para cada categoria para a qual deseja acompanhar as horas.

      dl-workforce-hours.png
       
    3. Clique em Adicionar horas para confirmar.
  5. Clique em Criar.

 