Add Financial Markup to Funding Change Orders
Objective
To add financial markup to a Funding Change Order (FCO).
Background
In Procore, the term financial markup is used to refer to an increase that is applied to the cost of a product or service in order to arrive at its final cost. The Funding tool lets users with 'Admin' permission set the markup amounts on your line items automatically. Using the settings in the project's Funding tool, you can set two types of financial markup:
- Horizontal Markup. A horizontal markup calculates the markup amount on an individual line item.
- Vertical Markup. A vertical markup calculates the markup amount as a subtotal on all of the line items on an FCO.
In addition, you can associate your financial markup settings to cost codes, categories, and sub jobs. This ensures that the financial markup on your project's FCOs is reflected accurately on your project's budget.
Things to Consider
- Required User Permissions:
- To add financial markup, 'Admin' level permissions on the project's Funding tool.
- To view financial markup on the change order's Schedule of Values (SOV), 'Standard' level permission on both the project's Change Orders and Funding tools.
- Additional Information:
- If you do NOT map the financial markup to a specific budget code, it appears in the budget as an unbudgeted line item.
- For companies using the ERP Integrations tool: Show/Hide
- Integração do Procore: Viewpoint® Spectrum®: Vertical and Horizontal.
- Integração do Ryvit: Viewpoint® Vista™. Vertical and Horizontal
- QuickBooks® Desktop. Markup is NOT supported.
- Sage 100 Contractor®. Markup is NOT supported.
- Sage 300 CRE®. Only vertical markup is supported when the following is true:
- Complete the steps in Request to Enable the ERP Integrations Tool.
- Configure the ERP Integrations tool. See Sage 300 CRE®: Setup Guide.
Prerequisites
- Add the Budget tool to your project. See Add and Remove Project Tools.
- Your company's Procore Administrator must do the following:
- Complete the steps in Create Your Company's Default Work Breakdown Structure and Enable Sub Jobs for WBS.
- Complete the steps in Create Your Project's Work Breakdown Structure and Add Sub Jobs to a Project.
- Enable the Financial Markup tab on the funding. See Enable Financial Markup on a Funding.
- Create at least one (1) funding. See Create Fundings.
Steps
- Navigate to the project's Funding tool.
- Locate the funding to work with. Then click its Number link.
- Click the Financial Markup tab.
Note
The 'Financial Markup' tab must be enabled in the funding's Advanced Settings tab. See Enable Financial Markup on a Funding. - Under Add Markups to Get Started, you have these options:
- Add Horizontal Markup. Click this button to display the markup in the same row as the line items.
- Add Vertical Markup. Click this button to display the markup below the line items.
Notes
- To learn about the differences between markup types, see What is the difference between horizontal and vertical financial markup on funding change orders?
- You can apply financial markup settings on a per-change order basis.
- Enter information in the Markup List as follows:
- Markup Name. Enter a name for the financial markup.
- Markup Percentage. Enter the percentage for the markup.
- Compounds Markup Above. Move the toggle to the right to compound your new markup. This setting is turned OFF by default.
- Under Maps To, do the following:
- Budget Code. Select the budget code that the markup percentage will be applied to. To learn more, see What is a budget code in Procore's WBS?
- Applies To. Choose the cost types that the markup percentage will be applied to. By default, Procore lists all of your existing cost types, so you can click the X on each cost type object to remove it. See What are Procore's default cost types? and Add Company Cost Types. If you want to remove one or more cost types, click the 'x' next to the desired selections.
- For companies using the ERP Integrations tool:
- ERP funding Item. Select the desired Schedule of Values (SOV) line item from the project’s funding. This ensures that the estimated value (the SOV value without vertical markup) and the revenue value (the SOV value with vertical markup) are synced to the line item that you specify in the integrated ERP system.
Notes
This field is only visible when:- Your company account has enabled the ERP Integrations tool.
- The ERP Integrations tool is configured to use either the Integração do Ryvit or Sage 300 CRE®.
- You are creating vertical markup on a funding change order.
- Export Markup to Estimate. Select this checkbox to enable the ability to sync financial markup on a funding to the cost estimate in ERP. This checkbox is only available to customers with the Sage 300 CRE® integration, Integração do Procore with Viewpoint® Spectrum®, or Integração do Ryvit with Viewpoint® Vista™ .
- ERP funding Item. Select the desired Schedule of Values (SOV) line item from the project’s funding. This ensures that the estimated value (the SOV value without vertical markup) and the revenue value (the SOV value with vertical markup) are synced to the line item that you specify in the integrated ERP system.
- Click Save.